Citrus Grove Phase 5

Lake County, Florida 2024-2025

Owner Information

Lake County BOCC

Designer Information

DRMP Engineering

Details of Work Performed

Project is located between Minneola and Montverde in South Lake County consisting of the construction of a new two-lane roadway approximately 4,100 feet in length connection on both sides of a newly constructed bridge over the Florida Turnpike.

Improvements include,

  • Constructing a 12’ Multiuse trail
  • Curb & Gutter
  • MSE wall
  • Storm drainage
  • Stabilization
  • Base & Asphalt paving
  • Signage & Pavement markings
  • Landscaping